|
Large Groundwater Withdrawal Permitting Process for Major Projects
In 1998 two state laws, the Groundwater Protection Act and the Safe Drinking Water Act, were amended to ensure that undesirable impacts to water resources from large new groundwater withdrawals are identified and mitigated. As a result, any new groundwater withdrawal from wells that equals or exceeds 57,600 gallons over any 24-hour period is considered to be a large groundwater withdrawal and must obtain a permit from the New Hampshire Department of Environmental Services. Amendments to the laws require the large groundwater withdrawal applicant to develop a conservation plan that demonstrates the need for the proposed withdrawal and to send copies of all application materials submitted to DES to each municipality and community water supplier located in the study area of a proposed withdrawal.
DES and an advisory committee, consisting of representatives from environmental organizations, municipali-ties, water suppliers, and a variety of potentially impacted businesses, worked together to develop the large groundwater withdrawal rules (Env-Ws 387 and Env-Ws 388) as required by the legislative amendments. The rules establish a permitting process and decision-making criteria for siting new large groundwater withdrawals. DES formally adopted the rules in April 2001.
The permitting process includes a two-tiered approach for assessing potential impacts that may be caused by a proposed withdrawal. A new large groundwater withdrawal is designated as either minor or major, based upon the magnitude of the proposed withdrawal and/or the potential impacts associated with developing a new withdrawal at a given site. Minor withdrawals are those with extraction rates ranging from 57,600 to 144,000 gallons per day (40–100 gallons per minute over any 24-hour period) and in an area with few water users and natural resources. Major withdrawals are those that exceed 144,000 gallons a day or are in an area with a sig-nificant number of water users or natural resources.
The permitting process for major withdrawals is detailed in Env-Ws 388, Major Groundwater Withdrawals, and generally consists of the following steps.
- Preliminary Permit Application
Submit a preliminary large groundwater withdrawal permit application, including the following:
- A Large Groundwater Withdrawal Permit Application Notification Form.
- Preliminary demonstration of need and proposed withdrawal volume.
- Preliminary conservation management plan.
- Preliminary delineation of study area including the maximum extent of the withdrawal’s cone of de-pression; the maximum extent of the withdrawal's recharge area; and the withdrawal’s downgradient area.
- Preliminary list of water users and a water resources inventory.
- Conceptual hydrologic model.
- Identification of data gaps in the conceptual hydrologic model.
- A proposed withdrawal testing design.
- An estimate of the withdrawal’s effects.
- Public Notification
The applicant must send by certified mail a copy of the preliminary permit application, and any subsequent application materials, to all municipalities and community water suppliers located in the study area of a pro-posed withdrawal.
- Preliminary Application Public Hearing
Pursuant to RSA 485-C:21, a municipality or water supplier located in the study area has 15 days after the re-ceipt of the preliminary permit application to request DES conduct a pubic hearing. The public hearing must be conducted within 30 days of the request.
- Preliminary Application 45-Day Public Comment Period
A 45-day public comment period follows the public hearing. If a hearing is not requested, the 45-day public comment period follows the date the preliminary permit application was received by the municipality or water supplier. DES considers all relevant recommendations and comments received during the 45-day comment period or at the public hearing.
- Optional Pre-Testing Conference and Revised Withdrawal Testing Design
During the 45-day public comment period, the applicant may request a pre-testing conference and a DES walk-through of the proposed withdrawal site. After a pre-testing conference and site walk-through, DES must comment on the adequacy of the proposed withdrawal testing design for assessing impacts to exist-ing water users and environmental resources. The applicant is strongly encouraged to revise the withdrawal testing design to address all DES comments and relevant technical issues identified during the public comment period.
- Withdrawal Testing
After revising the withdrawal testing design, the applicant conducts the withdrawal testing program. DES staff conducts site visits during withdrawal testing.
- Final Report
After completing withdrawal testing, the applicant must submit a final report to DES. The report must contain the following:
- A revised withdrawal permit volume– A revised permit volume may be requested provided the revised volume is less than or equal to the withdrawal volume demonstrated during withdrawal testing.
- Final conservation management plan that demonstrates need.
- Revised list of water users and water resources inventory.
- Revised delineation of study area.
- Revised conceptual hydrologic model based on data collected during withdrawal testing.
- A detailed description of the withdrawal testing program.
- A detailed analysis, including all calculations and collected data that fully summarizes the withdrawal testing results.
- A full assessment of impacts or potential impacts from the proposed withdrawal to existing water users or natural resources.
- A proposed monitoring and reporting program designed to ensure that adverse impacts will not occur as a result of the proposed withdrawal.
- A proposed plan, if necessary, to mitigate any potential adverse impacts should they occur.
- Final Report Public Hearing
Pursuant to RSA 485-C:21, a municipality or water supplier located in the study area has 15 days after the re-ceipt of the final report to request DES conduct a pubic hearing. The public hearing must be conducted within 30 days of the request.
- Final Report 45-Day Public Comment Period
A 45-day public comment period follows the public hearing. If a hearing is not requested, the 45-day public comment period follows the date the final report was received by the municipality or water supplier. DES con-siders all relevant recommendations and comments received during the 45-day comment period or at the public hearing.
- Technical Review
DES completes a technical review for a proposed large groundwater withdrawal within 45 days of a public hearing as described above or, if no hearing is requested, within 45 days of receipt of the final report. Using the adverse impact criteria in Env-Ws 388, DES evaluates the permit application to verify that adverse impacts will not occur as a result of the proposed withdrawal. Adverse impacts are defined in Env-Ws 388 as the following:
- Final Decision
If the permit application information demonstrates the withdrawal will not produce adverse impacts, DES will issue a large groundwater withdrawal permit. If the permit application information indicates that an adverse impact may occur, but can be mitigated, a withdrawal permit shall be granted under the following conditions:
- Sufficient information is provided verifying that any adverse impact will not be immediate or irre-versible.
- Adverse impacts can be prevented by mitigation.
- A monitoring and reporting program is implemented as approved by DES.
If insufficient permit application information exists for DES to complete a technical evaluation, depending upon the proposed large groundwater withdrawal potential impacts, DES will either:
- Issue a conditional approval contingent upon the results of monitoring and reporting requirements; or
- Require that additional hydrogeologic testing be completed for the withdrawal prior to issuing a permit.
Public Participation
DES recognizes that numerous stakeholders are often interested in the large groundwater withdrawal permit-ting process after the public hearing(s) and comment period portions have been completed. Therefore, DES is always available to meet and discuss technical issues relating to the proposed withdrawal permitting process. Furthermore, all documents, reports, and data submitted to DES regarding the withdrawal are available for review, by appointment, at our offices located at 29 Hazen Drive in Concord. Additionally, DES will provide each municipality with copies of any mailed correspondence sent to the applicant and will provide the appli-cant with copies of any mailed correspondence sent to or received from each municipality. DES will coordi-nate and conduct public information meetings and/or technical working sessions with project stakeholders dur-ing the permitting process where there is sufficient interest.
For Additional Information
Contact Christine Bowman at (603) 271-8866 or Christine.Bowman@des.nh.gov, or Stephen Roy at (603) 271-3918 or sroy@des.state.nh.us. The large groundwater withdrawal regulations can be found at www.des.state.nh.us/dwspp/lgwith.htm.
Please contact the Drinking Water and Groundwater Bureau at (603) 271-2513 or dwgbinfo@des.state.nh.us or visit our website at www.des.nh.gov/dwgb. All of the bureau’s fact sheets are on-line at www.des.nh.gov/dwg.htm.
Note: This fact sheet is accurate as of January 2007. Statutory or regulatory changes, or the availability of additional in-formation after this date may render this information inaccurate or incomplete.
|